EIEIOTECHNOVATION
← Training programmes

EIEIO / PROJECT MANAGEMENT

Course Agenda Project Management Professionals

Course outline

Duration to discuss

Duration

5 Days (7 hours/ per day), 16-20 Aug

Training Programme Days

DAY 1:

Monday

DAY 2:

Tuesday

DAY 3:

Wednesday

DAY 4:

Thursday

DAY 5:

Friday

THE DETAILED PROGRAM

DAY 1:

Session

Venue

From

To

Item

Virtual Instructed LED Training (VILT )

8.30 am

9.00 am

MODULE 1: Framework

  • Certification process to become a PMP®
  • Define processes, methodologies, and concepts within the9 knowledge areas

10.30 am

10:45 am

Morning Break

10.45 am

11.00 pm

  • Define key terms
  • Describe application of principles and techniques to manage projects
  • Personal expectations correlated to learning objectives
  • Identify need for Project Management

11:00 pm

12:00pm

MODULE 2: Professional Responsibility

  • Legal, ethical, and professional behaviour

1:00 pm

2:00pm

  • Lunch

2:00pm

3:00pm

  • Relationship of professional responsibility domain and the 10 areas of knowledge in the PMBOK® 5th

Edition Guide

3:00 pm

3:30 pm

  • Code of conduct

3:30 pm

3:45 pm

  • Afternoon Break

3:45 pm

4:00 pm

  • Cultural sensitivity in International Project Management

4:00pm

5:00pm

  • Course materials

END

DAY 2:

Session

Venue

From

To

Item

Virtual Instructed LED Training (VILT )

8.30 am

9.00 am

MODULE 3: PMP® Preparation

  • Review of PMP® Certification process

10.30 am

10:45 am

Morning Break

10.45 am

11.00 pm

  • Test-taking strategies

11:00 pm

12:00pm

  • Review of the 5 project management process areas and the professional responsibility domain  Review the 10 knowledge areas

1:00 pm

2:00pm

  • Lunch

2:00pm

3:00pm

MODULE 4: Project Integration Management

4.1 Develop Project Charter

4.2 Develop Project Management Plan

3:00 pm

3:30 pm

4.3 Direct & Manage Project Work

4.4 Monitor & Control Project Work

4.5 Perform Integrated Change Control

4.6 Close Project or Phase

3:30 pm

3:45 pm

  • Afternoon Break

3:45 pm

4:00 pm

4.5 Perform Integrated Change Control

4:00pm

5:00pm

  • 4.6 Close Project or Phase

END

DAY 3:

Session

Venue

From

To

Item

Virtual Instructed LED Training (VILT )

8.30 am

9.00 am

MODULE 5: Project Scope Management

5.1 Plan Scope Management

5.2 Collect Requirements

10.30 am

10:45 am

Morning Break

10.45 am

11.00 pm

5.3 Define Scope

5.4 Create WBS (Work Breakdown Structure)

11:00 pm

12:00pm

5.5 Validate Scope

5.6 Control Scope

1:00 pm

2:00pm

  • Lunch

2:00pm

3:00pm

MODULE 6: Project Time Management

6.1 Plan Schedule Management

6.2 Define Activities

3:00 pm

3:30 pm

6.3 Sequence Activities

3:30 pm

3:45 pm

  • Afternoon Break

3:45 pm

4:00 pm

4:00pm

5:00pm

6.4 Estimate Activity Resources

6.5 Estimate Activity Durations

6.6 Develop Schedule

6.7 Control Schedule

END

DAY 4:

Session

Venue

From

To

Item

Virtual Instructed LED Training (VILT )

8.30 am

9.00 am

MODULE 8: Project Quality Management

8.1 Plan Quality Management

10.30 am

10:45 am

Morning Break

10.45 am

11.00 pm

8.2 Perform Quality Assurance

11:00 pm

12:00pm

8.3 Control Quality

1:00 pm

2:00pm

  • Lunch

2:00pm

3:00pm

MODULE 9: Project Human Resource Management

9.1 Plan Human Resource Management

9.2 Acquire Project Team

9.3 Develop Project Team

9.4 Manage Project Team

3:00 pm

3:30 pm

MODULE 10: Project Communications Management

10.1 Plan Communications Management

3:30 pm

3:45 pm

  • Afternoon Break

3:45 pm

4:00 pm

10.2 Manage Communications

4:00pm

5:00pm

10.3 Control Communications

END

DAY 5:

Session

Venue

From

To

Item

Virtual Instructed LED Training (VILT )

8.30 am

9.00 am

MODULE 11: Project Risk Management

11.1 Plan Risk Management

11.2 Identify Risks

10.30 am

10:45 am

Morning Break

10.45 am

11.00 pm

11.3 Perform Qualitative Risk Analysis

11.4 Perform Quantitative Risk Analysis

11.5 Plan Risk Responses

11.6 Control Risks

11:00 pm

12:00pm

MODULE 12: Project Procurement Management

12.1 Plan Procurement Management

1:00 pm

2:00pm

  • Lunch

2:00pm

3:00pm

12.2 Conduct Procurements

12.3 Control Procurements

3:00 pm

3:30 pm

12.4 Close Procurements

MODULE 13: Project Stakeholder Management

13.1 Identify Stakeholders

3:30 pm

3:45 pm

  • Afternoon Break

3:45 pm

4:00 pm

13.2 Plan Stakeholder Management

4:00pm

5:00pm

13.3 Manage Stakeholder Engagement

13.4 Control Stakeholder Engagement

END

Programme scope, delivery arrangements and suitability are confirmed during enquiry.